Healthcare MEP

J&M Brown Company Nearing Completion on Signature Healthcare Brockton Hospital Fire Recovery Project

New hospital entrance signage and lighting was installed.

Brockton, MA – J&M Brown Company (JMB) is nearing completion on the comprehensive, electrical infrastructure reconstruction project at Signature Healthcare Brockton Hospital in Brockton.

The hospital reopened in mid-August, 18 months after the 10-alarm February 2023 electrical equipment room fire had forced the immediate, emergency closure of the hospital. The arcing electrical fire caused failure of the hospital’s electrical system, including normal power, generator power, lighting, emergency lighting, elevators, telecommunications, and oxygen system, and required the evacuation of 162 patients in coordination with the Brockton Fire Department and EMS resources from around the state.

The project entailed electrical and lighting installations for the new hospital lobby.

Within one week of the fire, J&M Brown was called upon by Signature Healthcare to assess the facility’s electrical systems and deliver design-assist/electrical construction recovery services. The multifaceted electrical reconstruction project scope entailed installation of the 5-story healthcare facility’s all new primary and emergency power systems, comprised of new electrical switchboards and electrical distribution panels throughout, as well all new electrical feeders and branch wiring. Emergency power is delivered by three new generators.

The hospital’s existing lighting was replaced with new LED lighting panels controlled by a new, advanced nLight lighting control system. The project also encompassed electrical installations for the hospital’s updated emergency department, updated catheterization lab, and new case management department, as well as the facility’s entirely renovated lobby, pharmacy, cafe, and kitchen.

During the course of the project, J&M Brown’s Fire Alarm Division also installed a new, state-of-the-art Autocall fire alarm system and Bi-directional antenna system to replace the hospital’s existing 40-year-old fire alarm system. The existing system was operational and kept on-line until parallel installation of the new life safety system was complete. JMB then enabled cutover to the new fire alarm system and provided removal of the old system. The NECA Boston contractor managed detailed electrical system and fire alarm system testing services with its subcontractor United Power Group, and working in close coordination with Brockton Inspectional Services, the Brockton Fire Department, and Signature Healthcare.

During the initial planning phase, J&M Brown worked with Signature Healthcare in the planning and then construction of a new electrical building, separated from the main hospital as a preventative measure. The building houses all major electrical and power supply components, and power is fed from utility power.

One of three new solar canopy parking areas

JMB also completed the fast-track installation of four solar arrays composed of a total of 3,243 solar panels on the four parking area canopies concurrent to the electrical reconstruction project. The solar project will generate 1.5MW of renewable power, helping to significantly reduce the facility’s electrical budget and offset its carbon footprint.

J&M Brown is performing the electrical restoration with a project team headed by Project Executive Michael Booker and General Foreman Phil Talbot managing an electrical crew ranging upwards of 50 IBEW electricians, based out of Local 223 in Brockton and Local 103 in Boston.

“J&M Brown is proud to have been called upon to achieve the comprehensive electrical restoration of Signature Healthcare Brockton Hospital, a project critical to Brockton and neighboring South Shore communities,” said Booker.  “It was a true collaborative effort, requiring close coordination with Signature Healthcare Brockton Hospital facility management, general contractor Auburn Construction, the City of Brockton Fire Department, numerous state agencies, and the support of key electrical vendors, as well as the dedication and expertise of our team of Local 223 and Local 103 electricians.”

Brian Backoff, Signature Healthcare Brockton Hospital director of facilities and engineering, said,  “An electrical fire of that magnitude meant that we [had] to rewire the entire 250,000sf hospital. “Wiring a hospital is a monumental task even for new construction. Retrofitting a hospital with new wiring and electrical and other infrastructure is even more challenging.”