Jaffrey, NH – Vantage Builders, Inc. announced it completed an 8,200sf, ground-up construction project for Teleflex Incorporated at its Teleflex Medical OEM facility in Jaffrey.

The project consisted of the construction of a new extrusion tower. The tower was needed to meet the expanding demand for Teleflex Medical OEM’s precision extrusion and access devices used in cardiology, neurology, radiology, and other areas.

Teleflex’s new extrusion tower consists of four stories and was built as an addition to its existing facility at 50 Plantation Drive in Jaffrey. As the facility runs 24/7, the project required careful coordination and scheduling between the project team members and Teleflex. Additionally, the Vantage team and the subcontractors put in extended hours onsite and performed weekend work when required.

The Vantage team began with site work to prepare the area. The project included new concrete foundations, structural steel, and significant systems work. The tower features new, dedicated MEP and fire protection, connected into Teleflex’s existing systems. The walls of the tower feature exterior thermal and moisture insulation with matching metal paneling. Epoxy flooring throughout is designed to provide safety and maintenance benefits.

The project team included Lavallee Bresinger Architects, NV5, CBRE, and Miller Engineering & Testing.